Pangalan ng vendor / Kontratista | Petsa ng Simula | Petsa ng Pagtatapos | Paggamit ng Maliit na Negosyo2 | Halaga ng kontrata (A) | Naka-encumer na Halaga FY2018-19 | Tunay na Gastos (B) | Balanse (A - B = C) | Tinatayang Gastos FY2018-19 | Mga Tinantyang Gastos (sa pamamagitan ng term ng kontrata) | Paglalarawan ng Serbisyo |
---|---|---|---|---|---|---|---|---|---|---|
AbleGov * | 0.0% | $3,172 | $3,172 | $0 | $3,172 | $3,172 | $3,172 | Adobe Designer | ||
Akin Gump Strauss Hauer & Feld, LLP | 4/11/17 | 2/28/20 | NA | $1,000,000 | $356,737 | $168,376 | $831,624 | $409,773 | $1,000,000 | Legal na payo para sa mga clearance sa kapaligiran at mga permit |
Pangkat ng Mga Serbisyo sa Konstruksyon ng Alliant Insurance Services Inc. | 9/23/14 | 7/24/19 | NA | $1,056,053 | $0 | $990,050 | $66,003 | $0 | $1,056,053 | Insurance broker at mga administratibong serbisyo para sa konstruksyon |
Allsteel * | 0.0% | $43,411 | $43,411 | $0 | $43,411 | $0 | $43,411 | Modular na kasangkapan - San Jose | ||
Allsteel * | 100.0% | $13,918 | $554 | $13,364 | $554 | $13,918 | $13,918 | Modular na kasangkapan - Sacramento | ||
Allsteel * | 0.0% | $31 | $0 | $0 | $31 | $31 | $31 | Mga kagamitan sa opisina | ||
Ang Arcadis US Inc. | 11/7/14 | 7/31/19 | 30.7% | $71,844,690 | $5,772,872 | $62,378,883 | $9,465,807 | $15,436,194 | $71,844,690 | Pamamahala ng Proyekto at Konstruksyon para sa CP2 -3 |
Ang Arcadis US Inc. | -$6,000,000 | $0 | $0 | -$6,000,000 | $0 | -$6,000,000 | Susugan ang #1 - Suriin ang saklaw; Bawasan ang pondo | |||
Ang Arcadis US Inc. | $7,100,000 | $0 | $0 | $7,100,000 | $0 | $7,100,000 | Susugan ang #2 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $72,944,690 | $5,772,872 | $62,378,883 | $10,565,807 | $15,436,194 | $72,944,690 | ||||
Associated Right of Way Services, Inc. | 3/20/17 | 2/28/21 | 91.5% | $7,330,000 | $2,362,317 | $1,805,493 | $5,524,507 | $3,092,413 | $7,330,000 | Magbigay ng mga serbisyong right-of-way at real estate |
Associated Right of Way Services, Inc. | $3,500,000 | $0 | $0 | $3,500,000 | $0 | $3,500,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Subtotal | $10,830,000 | $2,362,317 | $1,805,493 | $9,024,507 | $3,092,413 | $10,830,000 | ||||
Avantpage * | 0.0% | $65 | $65 | $0 | $65 | $65 | $65 | Mga serbisyo sa pagsalin | ||
Mga Pagsasalin ng Avantpage * | 0.0% | $652 | $0 | $0 | $652 | $652 | $652 | Mga serbisyo sa pagsalin | ||
Depot ng Mga Mamimili ng Axe * | 0.0% | $194 | $194 | $0 | $194 | $194 | $194 | Mga kagamitan sa opisina | ||
Baker at Miller PLLC | 9/28/15 | 12/31/20 | NA | $2,000,000 | $211,641 | $240,534 | $1,759,466 | $621,646 | $2,000,000 | Magbigay ng ligal na payo na nauugnay sa paglilitis na kinasasangkutan ng Federal Transportation Board |
Baker at Miller PLLC | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Baker at Miller PLLC | -$500,000 | $0 | $0 | -$500,000 | $0 | -$500,000 | Susugan ang #2 - Bawasan ang pagpopondo | |||
Baker at Miller PLLC | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #3 - Palawakin ang term ng kontrata | |||
Subtotal | $1,500,000 | $211,641 | $240,534 | $1,259,466 | $621,646 | $1,500,000 | ||||
Hamner, Jewell, & Associates, isang dibisyon ng Beacon Integrated Professional Resources, Inc. | 1/14/15 | 10/31/19 | 99.9% | $4,227,000 | $0 | $4,227,000 | $0 | $82,725 | $4,227,000 | Magbigay ng mga serbisyong right-of-way at real estate |
Hamner, Jewell, & Associates, isang dibisyon ng Beacon Integrated Professional Resources, Inc. | $773,000 | $0 | $757,855 | $15,145 | $773,000 | $773,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Hamner, Jewell, & Associates, isang dibisyon ng Beacon Integrated Professional Resources, Inc. | $977,000 | $0 | $97,671 | $879,329 | $314,819 | $977,000 | Susugan ang #2 - Taasan ang pagpopondo | |||
Hamner, Jewell, & Associates, isang dibisyon ng Beacon Integrated Professional Resources, Inc. | -$250,000 | $0 | $0 | -$250,000 | $0 | -$250,000 | Susugan ang #3 - Bawasan ang pagpopondo | |||
Hamner, Jewell, & Associates, isang dibisyon ng Beacon Integrated Professional Resources, Inc. | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #4 - Palawakin ang term ng kontrata | |||
Subtotal | $5,727,000 | $0 | $5,082,527 | $644,474 | $1,170,545 | $5,727,000 | ||||
Bender Rosenthal, Inc. | 3/20/17 | 2/28/21 | 14.4% | $7,330,000 | $3,939,853 | $2,531,648 | $4,798,352 | $4,600,829 | $7,330,000 | Magbigay ng mga serbisyong right-of-way at real estate |
Bender Rosenthal, Inc. | $3,500,000 | $0 | $0 | $3,500,000 | $0 | $3,500,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Subtotal | $10,830,000 | $3,939,853 | $2,531,648 | $8,298,352 | $4,600,829 | $10,830,000 | ||||
BNSF Railway Company ("BNSF") | 2/13/15 | 9/30/19 | NA | $5,000,000 | $784 | $4,999,216 | $784 | $1,002,297 | $5,000,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
BNSF Railway Company ("BNSF") | 12/20/16 | 12/31/21 | NA | $12,040,600 | $7,493,629 | $4,546,971 | $7,493,629 | $8,810,865 | $12,040,600 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Kumpanya ng BNSF Railway | 2/14/18 | 6/30/19 | NA | $2,000,000 | $470,672 | $1,040,672 | $959,328 | $1,000,000 | $2,000,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Bridge Micro * | 0.0% | $26,250 | $0 | $0 | $26,250 | $26,250 | $26,250 | Software | ||
Ang Briggs Field Services, Inc. | 1/14/15 | 10/31/19 | 74.6% | $3,885,000 | $297,341 | $3,587,659 | $297,341 | $478,617 | $3,885,000 | Magbigay ng mga serbisyong right-of-way at real estate |
Ang Briggs Field Services, Inc. | $250,000 | $250,000 | $0 | $250,000 | $0 | $250,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Ang Briggs Field Services, Inc. | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $4,135,000 | $547,341 | $3,587,659 | $547,341 | $478,617 | $4,135,000 | ||||
Burkett's Office Supply Inc * | 100.0% | $53 | $0 | $0 | $53 | $0 | $53 | Mga kagamitan sa opisina | ||
Burkett's Office Supply Inc * | 0.0% | $10 | $10 | $0 | $10 | $10 | $10 | Mga kagamitan sa opisina | ||
Burns & McDonnell Engineering Company, Inc. | 9/22/16 | 8/31/20 | NA | $890,000 | $302,786 | $108,798 | $781,202 | $317,704 | $890,000 | Kasunduan sa mga tauhan para sa mga ulat sa kapaligiran |
Burns & McDonnell Engineering Company, Inc. | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $890,000 | $302,786 | $108,798 | $781,202 | $317,704 | $890,000 | ||||
Capital Advantage * | NA | $521 | $39 | $482 | $39 | $521 | $521 | Direktoryo ng Kongreso | ||
Paghahatid ng C&C Express * | 90.0% | $497 | $50 | $447 | $50 | $497 | $497 | Mga kagamitan sa opisina | ||
Paghahatid ng C&C Express * | 0.0% | $320 | $320 | $0 | $320 | $320 | $320 | Mga kagamitan sa opisina | ||
Paghahatid ng C&C Express * | 0.0% | $261 | $261 | $0 | $261 | $261 | $261 | Mga kagamitan sa opisina | ||
CA Small Business Association * | NA | $150 | $150 | $0 | $150 | $150 | $150 | Pagpupulong | ||
Kagawaran ng Mga Parke at Libangan ng California | 9/25/14 | 12/31/22 | NA | $495,048 | $0 | $495,048 | $0 | $0 | $495,048 | Mapadali ang pagsusuri sa kapaligiran ng dokumentasyon ng mga mapagkukunang pangkultura |
Kagawaran ng Mga Parke at Libangan ng California | $922,401 | $0 | $922,401 | $0 | $325,867 | $922,401 | Susugan ang #1 - baguhin ang saklaw ng trabaho; pahabain ang term ng kontrata; dagdagan ang pondo | |||
Kagawaran ng Mga Parke at Libangan ng California | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Kagawaran ng Mga Parke at Libangan ng California | $2,318,746 | $0 | $0 | $2,318,746 | $0 | $2,318,746 | Susugan ang #3 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $3,736,195 | $0 | $1,417,449 | $2,318,746 | $325,867 | $3,736,195 | ||||
California Highway Patrol | 1/1/16 | 12/31/20 | NA | $49,714 | $3,082 | $46,632 | $3,082 | $0 | $49,714 | Mga serbisyo sa proteksyon |
California Highway Patrol | $259,000 | $111,814 | $2,133 | $256,867 | $0 | $259,000 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
California Highway Patrol | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $308,714 | $114,896 | $48,765 | $259,949 | $0 | $308,714 | ||||
California Highway Patrol | 3/12/19 | 8/31/19 | NA | $318,582 | $0 | $0 | $318,582 | $0 | $318,582 | Mga Check ng Pasilidad |
Museum sa California * | NA | $460 | $0 | $0 | $460 | $0 | $460 | Pagpaparenta ng Pasilidad | ||
California Rail Builders, LLC | 2/29/16 | 12/31/20 | 13.7% | $444,247,000 | $59,056,090 | $161,427,595 | $282,819,405 | $133,832,166 | $444,247,000 | Proyekto sa Konstruksiyon |
California Rail Builders, LLC | $44,416,002 | $0 | $0 | $44,416,002 | $0 | $44,416,002 | Kabuuan ng 31 na naisakatuparan na mga order ng pagbabago | |||
Subtotal | $488,663,002 | $59,056,090 | $161,427,595 | $327,235,408 | $133,832,166 | $488,663,002 | ||||
Pag-uulat ng California, LLC | 1/8/18 | 11/30/20 | NA | $11,000 | $4,588 | $6,412 | $4,588 | $1,400 | $11,000 | Mga sertipikadong serbisyo ng shorthand reporter at transcription |
Pag-uulat ng California, LLC | $22,000 | $11,000 | $0 | $22,000 | $0 | $22,000 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $33,000 | $15,588 | $6,412 | $26,588 | $1,400 | $33,000 | ||||
Kalihim ng Estado ng California * | NA | $3,750 | $2,625 | $1,125 | $2,625 | $2,625 | $3,750 | Rentahan ng silid | ||
Komisyon ng Mga Estado ng Lupa ng California | 1/26/19 | 11/30/23 | NA | $49,999 | $9,547 | $453 | $49,546 | $0 | $49,999 | Tulong sa pag-upa ng lupa |
CDW Government LLC * | NA | $86,020 | $86,020 | $0 | $86,020 | $86,020 | $86,020 | Kagamitan sa Kuryente | ||
Distrito ng Irigasyon ng Central California | 12/2/16 | 6/30/20 | NA | $143,527 | $121,688 | $16,005 | $127,522 | $121,688 | $143,527 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Distrito ng Irigasyon ng Central California | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $143,527 | $121,688 | $16,005 | $127,522 | $121,688 | $143,527 | ||||
CenturyLink Communication, LLC | 1/9/17 | 6/30/19 | NA | $19,100 | $3,000 | $0 | $19,100 | $3,000 | $19,100 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
CenturyLink Communication, LLC | 3/2/17 | 6/30/20 | NA | $27,260 | $13,630 | $0 | $27,260 | $13,630 | $27,260 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
CenturyLink Communication, LLC | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $27,260 | $13,630 | $0 | $27,260 | $13,630 | $27,260 | ||||
Chaudhary and Associates, Inc. | 3/28/14 | 6/30/21 | 98.3% | $3,200,000 | $0 | $3,200,000 | $0 | $0 | $3,200,000 | Kumuha ng mga kinakailangang survey sa lupa na may tama |
Chaudhary and Associates, Inc. | $400,000 | $0 | $400,000 | $0 | $0 | $400,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Chaudhary and Associates, Inc. | $1,400,000 | $2,863 | $1,397,137 | $2,863 | $2,863 | $1,400,000 | Susugan ang #2 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Chaudhary and Associates, Inc. | $706,367 | $706,367 | $0 | $706,367 | $0 | $706,367 | Susugan ang #3 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Chaudhary and Associates, Inc. | $2,925,000 | $493,633 | $0 | $2,925,000 | $0 | $2,925,000 | Susugan ang #4 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $8,631,367 | $1,202,863 | $4,997,137 | $3,634,230 | $2,863 | $8,631,367 | ||||
Lungsod ng Anaheim | 7/22/16 | 6/30/19 | NA | $352,259 | $135,469 | $14,531 | $337,728 | $150,000 | $352,259 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Bakersfield | 2/8/16 | 12/31/19 | NA | $401,607 | $122,728 | $114,650 | $286,957 | $129,676 | $401,607 | Pagbabayad para sa ligal na serbisyo, pagsisikap ng kawani, at kilalanin ang mga salungatan sa proyekto |
Lungsod ng Bakersfield | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $401,607 | $122,728 | $114,650 | $286,957 | $129,676 | $401,607 | ||||
Lungsod ng Bell | 12/16/16 | 6/1/19 | NA | $100,000 | $50,000 | $0 | $100,000 | $50,000 | $100,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Buena Park | 9/13/16 | 1/31/21 | NA | $83,097 | $40,000 | $0 | $83,097 | $40,000 | $83,097 | Pagpaplano sa kapaligiran |
Lungsod ng Buena Park | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $83,097 | $40,000 | $0 | $83,097 | $40,000 | $83,097 | ||||
Lungsod ng Burbank | 12/21/15 | 6/30/21 | NA | $800,000 | $250,000 | $139,945 | $660,055 | $250,000 | $800,000 | Pagpaplano ng Lugar ng Station |
Lungsod ng Burbank | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Lungsod ng Burbank | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $800,000 | $250,000 | $139,945 | $660,055 | $250,000 | $800,000 | ||||
Lungsod ng Burbank | 10/6/16 | 6/30/19 | NA | $242,362 | $100,000 | $0 | $242,362 | $100,000 | $242,362 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Komersyo | 7/18/16 | 1/31/21 | NA | $400,000 | $150,000 | $0 | $400,000 | $150,000 | $400,000 | Suriin ang mga salungatan sa mga utility |
Lungsod ng Komersyo | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $400,000 | $150,000 | $0 | $400,000 | $150,000 | $400,000 | ||||
Lungsod ng Fresno (Tandaan 13) | 6/7/12 | 12/31/19 | NA | $296,000 | $0 | $296,000 | $0 | $0 | $296,000 | Pamamahala sa peligro, ligal, mga pagpupulong ng proyekto |
Lungsod ng Fresno | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata; baguhin ang saklaw ng trabaho | |||
Lungsod ng Fresno | $200,000 | $0 | $200,000 | $0 | $0 | $200,000 | Susugan ang #2 - taasan ang pagpopondo; baguhin ang saklaw ng trabaho | |||
Lungsod ng Fresno | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #3 - Palawakin ang term ng kontrata | |||
Lungsod ng Fresno | $370,000 | $0 | $370,000 | $0 | $0 | $370,000 | Susugan ang #4 - Taasan ang pagpopondo | |||
Lungsod ng Fresno | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #5 - Palawakin ang term ng kontrata | |||
Lungsod ng Fresno | $555,000 | $149,535 | $213,013 | $341,987 | $176,026 | $555,000 | Susugan ang #6 - Taasan ang pagpopondo | |||
Lungsod ng Fresno | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #7 - Palawakin ang term ng kontrata | |||
Lungsod ng Fresno | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #8 - Palawakin ang term ng kontrata | |||
Subtotal | $1,421,000 | $149,535 | $1,079,013 | $341,987 | $176,026 | $1,421,000 | ||||
Lungsod ng Fresno | 9/28/16 | 6/30/20 | NA | $350,000 | $162,366 | $187,634 | $162,366 | $220,793 | $350,000 | G pagkakahanay sa kalye; tumulong sa koordinasyon ng mga pasilidad |
Lungsod ng Fresno | $5,215,000 | $4,809,906 | $0 | $5,215,000 | $4,794,207 | $5,215,000 | Susugan ang #1 - Palawakin ang kontrata; dagdagan ang pondo | |||
Subtotal | $5,565,000 | $4,972,273 | $187,634 | $5,377,366 | $5,015,000 | $5,565,000 | ||||
Lungsod ng Fresno | 1/5/17 | 6/30/20 | NA | $28,000,000 | $8,000,000 | $391,220 | $27,608,780 | $8,000,000 | $28,000,000 | Mga serbisyo sa pagtatayo ng overpass ng Veterans Blvd; at pagpapagaan ng pagsasara ng Carnegie Ave |
Lungsod ng Fresno | 9/13/18 | 12/31/19 | NA | $1,525,978 | $547,295 | $33,592 | $1,492,386 | $0 | $1,525,978 | Mga serbisyong pangkapaligiran na nauugnay sa pagpapalit ng lupa sa agrikultura |
Lungsod ng Fullerton | 11/21/16 | 6/30/19 | NA | $75,000 | $25,000 | $0 | $75,000 | $25,000 | $75,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Ang Lungsod ng Gilroy | 7/1/14 | 12/31/19 | NA | $600,000 | $240,000 | $334,587 | $265,413 | $150,000 | $600,000 | Pagpaplano ng Lugar ng Station |
Ang Lungsod ng Gilroy | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Suriin ang saklaw ng trabaho | |||
Ang Lungsod ng Gilroy | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $600,000 | $240,000 | $334,587 | $265,413 | $150,000 | $600,000 | ||||
Lungsod ng Gilroy | 12/12/16 | 6/30/21 | NA | $400,000 | $134,783 | $23,912 | $376,088 | $103,416 | $400,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Gilroy | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $400,000 | $134,783 | $23,912 | $376,088 | $103,416 | $400,000 | ||||
Lungsod ng Hanford | 6/12/14 | 12/31/20 | NA | $129,300 | $17,295 | $33,856 | $95,444 | $20,000 | $129,300 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Hanford | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Lungsod ng Hanford | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Lungsod ng Hanford | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #3 - Palawakin ang term ng kontrata | |||
Subtotal | $129,300 | $17,295 | $33,856 | $95,444 | $20,000 | $129,300 | ||||
Lungsod ng La Mirada | 9/7/16 | 1/31/21 | NA | $457,000 | $97,000 | $0 | $457,000 | $200,000 | $457,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng La Mirada | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $457,000 | $97,000 | $0 | $457,000 | $200,000 | $457,000 | ||||
Lungsod ng Lancaster | 12/13/16 | 6/30/21 | NA | $185,270 | $52,270 | $0 | $185,270 | $55,270 | $185,270 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Lancaster | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $185,270 | $52,270 | $0 | $185,270 | $55,270 | $185,270 | ||||
Lungsod ng Los Angeles | 10/13/16 | 6/30/19 | NA | $1,269,247 | $600,000 | $32,382 | $1,236,865 | $600,000 | $1,269,247 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Menlo Park | 4/17/17 | 12/31/19 | NA | $50,000 | $40,000 | $0 | $50,000 | $40,000 | $50,000 | Pagpaplano sa kapaligiran |
Lungsod ng Menlo Park | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $50,000 | $40,000 | $0 | $50,000 | $40,000 | $50,000 | ||||
Lungsod ng Merced | 9/12/13 | 12/31/19 | NA | $600,000 | $150,000 | $376,195 | $223,805 | $150,000 | $600,000 | Pagpaplano ng lugar ng istasyon |
Lungsod ng Merced | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata; baguhin ang saklaw ng trabaho | |||
Lungsod ng Merced | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Lungsod ng Merced | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #3 - Palawakin ang term ng kontrata | |||
Subtotal | $600,000 | $150,000 | $376,195 | $223,805 | $150,000 | $600,000 | ||||
Lungsod ng Millbrae | 5/7/19 | 10/31/20 | NA | $200,000 | $200,000 | $0 | $200,000 | $0 | $200,000 | Pagpaplano ng Lugar ng Station |
Lungsod ng Montebello | 10/28/16 | 6/30/19 | NA | $175,000 | $100,000 | $0 | $175,000 | $100,000 | $175,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Morgan Hill | 6/6/16 | 6/30/20 | NA | $409,641 | $83,746 | $240,654 | $168,987 | $84,157 | $409,641 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Morgan Hill | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $409,641 | $83,746 | $240,654 | $168,987 | $84,157 | $409,641 | ||||
Lungsod ng Norwalk | 7/1/16 | 1/31/21 | NA | $499,900 | $200,000 | $86,041 | $413,859 | $200,000 | $499,900 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Norwalk | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $499,900 | $200,000 | $86,041 | $413,859 | $200,000 | $499,900 | ||||
Lungsod ng Palmdale | 4/30/15 | 6/30/20 | NA | $600,000 | $0 | $515,909 | $84,091 | $0 | $600,000 | Pagpaplano ng Lugar ng Station |
Lungsod ng Palmdale | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Suriin ang saklaw ng trabaho | |||
Lungsod ng Palmdale | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Lungsod ng Palmdale | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #3 - Palawakin ang term ng kontrata | |||
Lungsod ng Palmdale | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #4 - Palawakin ang term ng kontrata | |||
Subtotal | $600,000 | $0 | $515,909 | $84,091 | $0 | $600,000 | ||||
Lungsod ng Palmdale | 8/23/16 | 6/30/19 | NA | $172,797 | $80,000 | $0 | $172,797 | $80,000 | $172,797 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng San Mateo | 11/14/16 | 12/31/19 | NA | $100,000 | $30,000 | $0 | $100,000 | $30,000 | $100,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng San Mateo | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $100,000 | $30,000 | $0 | $100,000 | $30,000 | $100,000 | ||||
Lungsod ng San Jose | 10/17/16 | 6/30/19 | NA | $270,000 | $0 | $270,000 | $0 | $0 | $270,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng San Jose | $599,688 | $174,349 | $268,028 | $331,661 | $182,392 | $599,688 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Lungsod ng San Jose | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $869,688 | $174,349 | $538,028 | $331,661 | $182,392 | $869,688 | ||||
Lungsod ng Santa Clara | 5/23/17 | 12/31/19 | NA | $150,644 | $120,515 | $0 | $150,644 | $120,515 | $150,644 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Santa Clara | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $150,644 | $120,515 | $0 | $150,644 | $120,515 | $150,644 | ||||
Lungsod ng Santa Fe Springs | 8/23/16 | 1/31/21 | NA | $499,000 | $200,000 | $0 | $499,000 | $200,000 | $499,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Santa Fe Springs | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $499,000 | $200,000 | $0 | $499,000 | $200,000 | $499,000 | ||||
Lungsod ng Timog San Francisco | 1/9/17 | 12/31/19 | NA | $35,000 | $17,500 | $0 | $35,000 | $17,500 | $35,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Timog San Francisco | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $35,000 | $17,500 | $0 | $35,000 | $17,500 | $35,000 | ||||
Lungsod ng Tehachapi | 10/17/16 | 1/31/21 | NA | $109,222 | $12,679 | $89,089 | $20,133 | $50,000 | $109,222 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Tehachapi | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $109,222 | $12,679 | $89,089 | $20,133 | $50,000 | $109,222 | ||||
Lungsod ng Vernon | 9/7/16 | 6/30/19 | NA | $425,118 | $198,355 | $1,645 | $423,473 | $200,000 | $425,118 | Serbisyong inhinyero |
Lungsod ng Wasco | 3/14/14 | 12/31/19 | NA | $205,658 | $82,263 | $0 | $205,658 | $82,263 | $205,658 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Lungsod ng Wasco | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Lungsod ng Wasco | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $205,658 | $82,263 | $0 | $205,658 | $82,263 | $205,658 | ||||
CompuVision * | 0.0% | $58,453 | $58,453 | $0 | $58,453 | $58,453 | $58,453 | Kagamitan sa IT | ||
Mga Serbisyo sa Continental Acqu acquisition, Inc. | 3/20/17 | 2/28/21 | 96.9% | $7,330,000 | $550,521 | $6,779,479 | $550,521 | $550,521 | $7,330,000 | Magbigay ng mga serbisyong right-of-way at real estate |
Mga Serbisyo sa Continental Acqu acquisition, Inc. | $3,500,000 | $2,114,407 | $0 | $3,500,000 | $0 | $3,500,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Subtotal | $10,830,000 | $2,664,928 | $6,779,479 | $4,050,521 | $550,521 | $10,830,000 | ||||
Patuloy na Edukasyon ng Bar * | NA | $3,622 | $0 | $3,622 | $0 | $0 | $3,622 | Mga ligal na libro at pag-update | ||
Mga Convergent System * | 0.0% | $4,080 | $4,080 | $0 | $4,080 | $4,080 | $4,080 | Mga serbisyo sa IT - Access Control System | ||
Mga Serbisyo ng Kooperasyong Personnel (CPS) | 9/5/18 | 6/30/20 | NA | $80,000 | $22,370 | $17,630 | $62,370 | $22,370 | $80,000 | HR - Pagsasanay |
County ng Fresno | 9/5/13 | 12/31/19 | NA | $3,197,459 | $141,809 | $638,058 | $2,559,401 | $200,000 | $3,197,459 | Tulong sa paglilipat ng negosyo |
County ng Fresno | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
County ng Fresno | -$2,158,565 | $0 | $0 | -$2,158,565 | $0 | -$2,158,565 | Susugan ang #2 - Palawakin ang term ng kontrata; bawasan ang pagpopondo ng kontrata | |||
Subtotal | $1,038,894 | $141,809 | $638,058 | $400,836 | $200,000 | $1,038,894 | ||||
County ng Fresno | 2/7/14 | 12/31/19 | NA | $204,400 | $5,046 | $151,738 | $52,662 | $41,593 | $204,400 | Suriin ang mga salungatan sa mga utility |
County ng Fresno | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata; baguhin ang saklaw ng trabaho | |||
County ng Fresno | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $204,400 | $5,046 | $151,738 | $52,662 | $41,593 | $204,400 | ||||
County ng Madera | 8/18/15 | 12/31/19 | NA | $57,054 | $31,579 | $10,304 | $46,750 | $31,579 | $57,054 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
County ng Madera | $7,531 | $0 | $0 | $7,531 | $0 | $7,531 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
County ng Madera | $24,666 | $0 | $0 | $24,666 | $0 | $24,666 | Susugan ang #2 - Suriin ang saklaw ng trabaho; dagdagan ang pondo | |||
County ng Madera | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #3 - Palawakin ang term ng kontrata | |||
Subtotal | $89,251 | $31,579 | $10,304 | $78,947 | $31,579 | $89,251 | ||||
County ng San Benito | 11/14/16 | 12/31/19 | NA | $100,000 | $50,000 | $0 | $100,000 | $50,000 | $100,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
County ng San Benito | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $100,000 | $50,000 | $0 | $100,000 | $50,000 | $100,000 | ||||
County ng Santa Clara | 12/16/16 | 12/31/19 | NA | $150,000 | $37,877 | $88,119 | $61,881 | $41,334 | $150,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
County ng Santa Clara | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $150,000 | $37,877 | $88,119 | $61,881 | $41,334 | $150,000 | ||||
County ng Tulare | 11/12/13 | 12/31/19 | NA | $151,400 | $27,136 | $87,576 | $63,824 | $31,597 | $151,400 | Suriin ang mga salungatan sa mga utility |
County ng Tulare | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
County ng Tulare | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $151,400 | $27,136 | $87,576 | $63,824 | $31,597 | $151,400 | ||||
Crown Worldwide Moving and Storage LLC | 10/9/18 | 6/30/19 | NA | $50,000 | $15,768 | $14,232 | $35,768 | $15,768 | $50,000 | Ang paglilipat ng mga serbisyo para sa mga panrehiyong tanggapan at punong tanggapan |
CSU, Fullerton Auxiliary Services Corporation | 2/16/16 | 6/30/20 | NA | $500,000 | $97,664 | $214,559 | $285,441 | $161,479 | $500,000 | Magsagawa ng mga pag-aaral upang tuklasin ang pakikipag-ugnayan sa pagitan ng mga mapagkukunan ng tubig sa lupa at mga sistema ng aquifer |
CSU, Fullerton Auxiliary Services Corporation | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
CSU, Fullerton Auxiliary Services Corporation | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $500,000 | $97,664 | $214,559 | $285,441 | $161,479 | $500,000 | ||||
DB Engineering & Consulting USA, Inc. | 12/19/17 | 11/30/23 | 13.3% | $30,000,000 | $1,457,161 | $5,953,906 | $24,046,094 | $1,457,161 | $30,000,000 | Maagang Operator ng Tren |
Kagawaran ng Konserbasyon ng California | 6/30/13 | 9/30/21 | NA | $19,993,339 | $1,193,754 | $11,406,951 | $8,586,388 | $14,867,243 | $19,993,339 | Magbigay ng mga serbisyo upang matugunan ang mga pangako sa kapaligiran na awtoridad na nauugnay sa pagbabago ng lupa sa agrikultura |
Kagawaran ng Konserbasyon ng California | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Suriin ang saklaw ng trabaho | |||
Kagawaran ng Konserbasyon ng California | $15,999,069 | $0 | $0 | $15,999,069 | $0 | $15,999,069 | Susugan ang #2 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Subtotal | $35,992,408 | $1,193,754 | $11,406,951 | $24,585,457 | $14,867,243 | $35,992,408 | ||||
Kagawaran ng Pangkalahatang Serbisyo | 12/21/15 | 10/31/19 | NA | $80,976 | $0 | $0 | $80,976 | $80,976 | $80,976 | Mga serbisyong Small Certification at Workshop ng negosyo |
Kagawaran ng Pangkalahatang Serbisyo | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $80,976 | $0 | $0 | $80,976 | $80,976 | $80,976 | ||||
Kagawaran ng Pangkalahatang Serbisyo-Opisina ng Paglathala ng Estado (DGS-OSP) | 10/9/18 | 12/31/19 | NA | $159,200 | $159,200 | $0 | $159,200 | $0 | $159,200 | Itala ang mga serbisyo sa imaging |
Kagawaran ng Isda at Wildlife ng California | 3/12/15 | 6/30/19 | NA | $1,469,269 | $0 | $1,469,269 | $0 | $0 | $1,469,269 | Ang tulong sa kapaligiran kabilang ang mga pagsusuri sa Patlang at pagkilala sa mga kritikal na mapagkukunang biyolohikal |
Kagawaran ng Isda at Wildlife ng California | $3,464,412 | $1,853,502 | $1,610,910 | $1,853,502 | $1,853,502 | $3,464,412 | Susugan ang #1 - Taasan ang pagpopondo; baguhin ang saklaw ng trabaho | |||
Kagawaran ng Isda at Wildlife ng California | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Kagawaran ng Isda at Wildlife ng California | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #3 - Palawakin ang term ng kontrata | |||
Subtotal | $4,933,681 | $1,853,502 | $3,080,179 | $1,853,502 | $1,853,502 | $4,933,681 | ||||
Kagawaran ng Kagawaran ng Kagubatan at Bumbero ng California (CAL FIRE) | 8/18/16 | 6/30/21 | NA | $6,000,000 | $1,000,000 | $0 | $6,000,000 | $1,000,000 | $6,000,000 | Mga serbisyong pagtatanim ng puno |
Kagawaran ng Human Resources | 7/30/18 | 6/30/19 | NA | $20,000 | $2,845 | $17,156 | $2,845 | $20,000 | $20,000 | Ang CalHR ay nagbibigay ng mga serbisyo sa pagkuha |
Kagawaran ng Human Resources | 7/30/18 | 6/30/21 | NA | $105,000 | $9,380 | $25,620 | $79,380 | $35,000 | $105,000 | Ang CalHR ay dapat magbigay ng mga serbisyo sa pagsasanay |
Departamento ng Transportasyon | 6/19/12 | 6/30/21 | NA | $7,086,000 | $0 | $7,086,000 | $0 | $0 | $7,086,000 | Mga serbisyong ligal para sa pamamahala ng real estate |
Departamento ng Transportasyon | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Departamento ng Transportasyon | $1,750,000 | $0 | $1,750,000 | $0 | $0 | $1,750,000 | Susugan ang #2 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Departamento ng Transportasyon | $3,600,000 | $0 | $3,600,000 | $0 | $0 | $3,600,000 | Susugan ang #3 - Taasan ang pagpopondo | |||
Departamento ng Transportasyon | $15,500,000 | $2,724,708 | $2,066,845 | $13,433,155 | $2,724,708 | $15,500,000 | Susugan ang #4 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $27,936,000 | $2,724,708 | $14,502,845 | $13,433,155 | $2,724,708 | $27,936,000 | ||||
Kagawaran ng Transportasyon ng California | 1/18/19 | 6/30/20 | NA | $225,900,000 | $0 | $225,900,000 | $0 | $0 | $225,900,000 | Mga Pagpapabuti sa Ruta ng Estado 99 |
Kagawaran ng Transportasyon ng California | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Suriin ang saklaw ng trabaho | |||
Kagawaran ng Transportasyon ng California | $35,000,000 | $5,977,264 | $29,022,736 | $5,977,264 | $22,871,110 | $35,000,000 | Susugan ang #2 - Taasan ang pagpopondo | |||
Kagawaran ng Transportasyon ng California | $29,200,000 | $15,830,577 | $5,816,729 | $23,383,271 | $0 | $29,200,000 | Susugan ang #3 - Taasan ang pagpopondo | |||
Subtotal | $290,100,000 | $21,807,842 | $260,739,465 | $29,360,535 | $22,871,110 | $290,100,000 | ||||
Departamento ng Transportasyon | 9/1/14 | 6/30/19 | NA | $74,106 | $15,196 | $45,014 | $29,092 | $24,838 | $74,106 | Caltrans Quickmap application |
Departamento ng Transportasyon | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Departamento ng Transportasyon | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $74,106 | $15,196 | $45,014 | $29,092 | $24,838 | $74,106 | ||||
Kagawaran ng Transportasyon ng California | 4/13/15 | 12/31/20 | NA | $3,180,000 | $185,476 | $2,994,524 | $185,476 | $185,476 | $3,180,000 | Independent kasiguruhan sa kalidad sa panahon ng mga plano, pagtutukoy, pagtantya, right-of-way at konstruksyon |
Kagawaran ng Transportasyon ng California | $530,000 | $277,282 | $0 | $530,000 | $0 | $530,000 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $3,710,000 | $462,758 | $2,994,524 | $715,476 | $185,476 | $3,710,000 | ||||
Kagawaran ng Transportasyon ng California (Caltrans) | 2/27/18 | 12/31/19 | NA | $4,800,000 | $985,379 | $1,917,647 | $2,882,353 | $2,300,000 | $4,800,000 | Independent kasiguruhan sa kalidad sa panahon ng mga plano, pagtutukoy, pagtantya, right-of-way at konstruksyon |
Departamento ng Transportasyon | 4/1/18 | 12/31/20 | NA | $4,980,050 | $1,521,738 | $401,647 | $4,578,403 | $68,000 | $4,980,050 | Nagbibigay ang Caltrans ng CHSRA ng mga pinahiram na dalubhasang kawani |
Departamento ng Transportasyon | 5/1/18 | 6/30/22 | NA | $640,000 | $160,000 | $0 | $640,000 | $0 | $640,000 | Independent kasiguruhan sa kalidad sa panahon ng mga plano, pagtutukoy, pagtantya, right-of-way at konstruksyon |
Departamento ng Transportasyon | 5/30/18 | 6/30/22 | NA | $4,130,000 | $1,062,594 | $7,406 | $4,122,594 | $1,070,000 | $4,130,000 | Independent kasiguruhan sa kalidad sa panahon ng mga plano, pagtutukoy, pagtantya, right-of-way at konstruksyon |
Departamento ng Transportasyon | 5/30/18 | 6/30/21 | NA | $3,530,000 | $385,653 | $524,347 | $3,005,653 | $0 | $3,530,000 | Independent kasiguruhan sa kalidad sa panahon ng mga plano, pagtutukoy, pagtantya, right-of-way at konstruksyon |
Kagawaran ng Transportasyon ng California | 12/11/18 | 9/30/21 | NA | $13,900 | $4,519 | $0 | $13,900 | $0 | $13,900 | Mga serbisyo sa relasyon sa paggawa |
Kagawaran ng Transportasyon ng California | 3/8/19 | 12/31/20 | NA | $4,920,000 | $1,230,000 | $0 | $4,920,000 | $0 | $4,920,000 | Mga Caltrans Independent Quality Assurance |
Dragados / Flatiron Joint Venture | 6/10/15 | 9/30/19 | 6.1% | $1,365,335,890 | $183,327,657 | $647,201,374 | $718,134,516 | $310,422,592 | $1,365,335,890 | Proyekto sa Konstruksiyon |
Dragados / Flatiron Joint Venture | $102,133,608 | $0 | $0 | $102,133,608 | $0 | $102,133,608 | Kabuuan ng 117 naipatupad na mga order ng pagbabago | |||
Subtotal | $1,467,469,498 | $183,327,657 | $647,201,374 | $820,268,124 | $310,422,592 | $1,467,469,498 | ||||
Ebbin Moser + Skaggs, LLP | 4/27/15 | 12/31/20 | NA | $750,000 | $0 | $750,000 | $0 | $0 | $750,000 | Legal na payo para sa mga clearance sa kapaligiran at mga permit |
Ebbin Moser + Skaggs, LLP | $750,000 | $0 | $750,000 | $0 | $0 | $750,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Ebbin Moser + Skaggs, LLP | $1,500,000 | $39,711 | $1,460,289 | $39,711 | $771,431 | $1,500,000 | Susugan ang #2 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Ebbin Moser + Skaggs, LLP | $3,600,000 | $1,398,808 | $0 | $3,600,000 | $0 | $3,600,000 | Susugan ang #3 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Subtotal | $6,600,000 | $1,438,519 | $2,960,289 | $3,639,711 | $771,431 | $6,600,000 | ||||
Ang Enterprise Networking Solutions Inc. | 10/15/18 | 6/30/21 | NA | $534,000 | $186,000 | $39,000 | $495,000 | $186,000 | $534,000 | Pagkonsulta sa IT |
Mga Kasama sa Agham sa Kapaligiran | 8/5/16 | 6/30/21 | 3.2% | $4,800,000 | $669,428 | $1,168,514 | $3,631,486 | $1,000,108 | $4,800,000 | Serbisyong pangkalikasan |
Equilon Enterprises LLC, dba Mga Produkto ng Langis ng Shell US | 2/7/14 | 12/31/19 | NA | $33,100 | $13,240 | $0 | $33,100 | $13,240 | $33,100 | Tumutulong sa koordinasyon at pagsusuri ng mga pasilidad na maaaring mangailangan ng paglipat bilang bahagi ng HSR Project |
Equilon Enterprises LLC, dba Mga Produkto ng Langis ng Shell US | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Equilon Enterprises LLC, dba Mga Produkto ng Langis ng Shell US | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $33,100 | $13,240 | $0 | $33,100 | $13,240 | $33,100 | ||||
Ernst & Young (Payong Pinansyal) | 6/23/16 | 6/14/20 | NA | $10,000,000 | $0 | $2,847,050 | $7,152,950 | $0 | $10,000,000 | Tagapayo sa pananalapi - Pangalawa |
Executive Maintenance, Inc. | 2/26/19 | 1/31/21 | NA | $50,140 | $6,268 | $4,178 | $45,962 | $0 | $50,140 | Mga serbisyo sa paglilinis |
Mga Produkto ng Express Office * | 0.0% | $24 | $0 | $0 | $24 | $24 | $24 | Mga kagamitan sa opisina | ||
Federal Express * | NA | $5,000 | $1,939 | $3,061 | $1,939 | $4,438 | $5,000 | Serbisyo ng magdamag na pag-mail | ||
Federal Express * | NA | $5,000 | $3,884 | $1,116 | $3,884 | $0 | $5,000 | Serbisyo ng magdamag na pag-mail | ||
Mga Kasosyo sa Pag-aalaga | 9/15/16 | 9/30/19 | NA | $3,000,000 | $654,531 | $2,307,128 | $692,872 | $654,531 | $3,000,000 | Plano ng paningin para sa mga istasyon |
Fresno Irrigation District | 7/29/15 | 12/31/19 | NA | $117,774 | $0 | $92,267 | $25,507 | $0 | $117,774 | Pagkilala ng mga pasilidad, pagbibigay ng dokumentasyon at oras ng kawani para sa koordinasyon |
Fresno Irrigation District | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $117,774 | $0 | $92,267 | $25,507 | $0 | $117,774 | ||||
Fresno Metropolitan Flood Control District | 10/20/16 | 6/30/19 | NA | $51,291 | $0 | $51,291 | $0 | $11,291 | $51,291 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Fresno Metropolitan Flood Control District | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $51,291 | $0 | $51,291 | $0 | $11,291 | $51,291 | ||||
Ang Frontier California, Inc. | 1/25/17 | 12/31/19 | NA | $21,225 | $17,433 | $0 | $21,225 | $17,433 | $21,225 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Ang Frontier California, Inc. | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $21,225 | $17,433 | $0 | $21,225 | $17,433 | $21,225 | ||||
Golden State Overnight * | NA | $4,200 | $2,538 | $1,662 | $2,538 | $0 | $4,200 | Serbisyo sa paghahatid | ||
Goodin, MacBride, Squeri & Day, LLP | 7/11/17 | 12/31/20 | NA | $302,500 | $0 | $302,500 | $0 | $176,448 | $302,500 | Legal na pagsusuri at suporta na nauugnay sa CPUC |
Goodin, MacBride, Squeri & Day, LLP | $1,300,000 | $546,288 | $14,713 | $1,285,287 | $0 | $1,300,000 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $1,602,500 | $546,288 | $317,213 | $1,285,287 | $176,448 | $1,602,500 | ||||
Opisina ng Pagpaplano at Pananaliksik | 1/31/14 | 12/31/19 | NA | $812,506 | $0 | $812,506 | $0 | $0 | $812,506 | Pagpopondo ng dalawang posisyon sa kapaligiran |
Opisina ng Pagpaplano at Pananaliksik | $266,823 | $0 | $266,823 | $0 | $0 | $266,823 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Opisina ng Pagpaplano at Pananaliksik | $54,279 | $0 | $54,279 | $0 | $0 | $54,279 | Susugan ang #2 - Taasan ang pagpopondo | |||
Opisina ng Pagpaplano at Pananaliksik | $308,268 | $0 | $308,268 | $0 | $0 | $308,268 | Susugan ang #3 - Taasan ang pagpopondo | |||
Opisina ng Pagpaplano at Pananaliksik | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #4 - Palawakin ang term ng kontrata | |||
Opisina ng Pagpaplano at Pananaliksik | $916,632 | $416,716 | $499,916 | $416,716 | $282,980 | $916,632 | Susugan ang #5 - Taasan ang pagpopondo | |||
Opisina ng Pagpaplano at Pananaliksik | $622,550 | $81,351 | $0 | $622,550 | $0 | $622,550 | Susugan ang #6 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $2,981,058 | $498,067 | $1,941,792 | $1,039,266 | $282,980 | $2,981,058 | ||||
Mga Solusyon sa Data ng Granite * | 100.0% | $2,915 | $0 | $2,896 | $18 | $0 | $2,915 | Kagamitan sa IT - Dell desktop | ||
Grassland Water District | 1/9/17 | 6/30/22 | NA | $101,442 | $23,712 | $15,405 | $86,037 | $23,712 | $101,442 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Grassland Water District | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $101,442 | $23,712 | $15,405 | $86,037 | $23,712 | $101,442 | ||||
Greenberg Traurig LLP | 11/4/15 | 12/31/20 | NA | $3,000,000 | $435,105 | $440,910 | $2,559,090 | $608,952 | $3,000,000 | Legal na pagsusuri at suporta na nauugnay sa disenyo-build |
Greenberg Traurig LLP | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Suriin ang saklaw ng trabaho | |||
Greenberg Traurig LLP | -$1,500,000 | $0 | $0 | -$1,500,000 | $0 | -$1,500,000 | Susugan ang #2 - Bawasan ang pagpopondo; pahabain ang term ng kontrata | |||
Subtotal | $1,500,000 | $435,105 | $440,910 | $1,059,090 | $608,952 | $1,500,000 | ||||
GSO * | NA | $10,000 | $213 | $9,787 | $213 | $7,824 | $10,000 | Maliit na paghahatid ng parsela | ||
Henry Miller Reclamation District #2131 | 3/14/17 | 6/30/20 | NA | $99,408 | $99,408 | $0 | $99,408 | $95,183 | $99,408 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Henry Miller Reclamation District #2131 | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $99,408 | $99,408 | $0 | $99,408 | $95,183 | $99,408 | ||||
Hernandez, Kroone & Associate | 3/28/14 | 6/30/21 | 100.0% | $3,200,000 | $0 | $3,200,000 | $0 | $0 | $3,200,000 | Kumuha ng mga kinakailangang survey sa lupa na may tama |
Hernandez, Kroone & Associate | $400,000 | $0 | $400,000 | $0 | $0 | $400,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Hernandez, Kroone & Associate | $1,693,634 | $0 | $1,693,634 | $0 | $0 | $1,693,634 | Susugan ang #2 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Hernandez, Kroone & Associate | $1,806,366 | $651,659 | $779,946 | $1,026,420 | $1,100,000 | $1,806,366 | Susugan ang #3 - Taasan ang pagpopondo | |||
Hernandez, Kroone & Associate | $2,725,000 | $0 | $0 | $2,725,000 | $0 | $2,725,000 | Susugan ang #4 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Subtotal | $9,825,000 | $651,659 | $6,073,580 | $3,751,420 | $1,100,000 | $9,825,000 | ||||
HKA - Global, Inc dba Hill International Consulting, Inc. | 4/21/17 | 12/31/20 | NA | $2,000,000 | $677,971 | $833,025 | $1,166,975 | $924,316 | $2,000,000 | Mga Serbisyo ng Dalubhasang Saksi |
HKA - Global, Inc dba Hill International Consulting, Inc. | $440,000 | $0 | $0 | $440,000 | $0 | $440,000 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $2,440,000 | $677,971 | $833,025 | $1,606,975 | $924,316 | $2,440,000 | ||||
HNTB Corporation | 1/8/16 | 12/31/20 | 23.2% | $30,064,017 | $0 | $30,064,017 | $0 | $6,887,221 | $30,064,017 | Mga serbisyo sa pamamahala ng pagtatayo ng proyekto |
HNTB Corporation | $12,800,000 | $8,238,148 | $3,874,694 | $8,925,306 | $0 | $12,800,000 | Susugan ang #1 - Palawakin ang term ng kontrata, dagdagan ang pagpopondo | |||
Subtotal | $42,864,017 | $8,238,148 | $33,938,711 | $8,925,306 | $6,887,221 | $42,864,017 | ||||
HNTB Corporation | 11/23/15 | 9/30/21 | 20.3% | $36,000,000 | $0 | $36,000,000 | $0 | $0 | $36,000,000 | Mga serbisyo sa Kapaligiran at Engineering |
HNTB Corporation | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Mga tuntunin sa pagsingil lamang | |||
HNTB Corporation | $10,000,000 | $0 | $10,000,000 | $0 | $4,880,597 | $10,000,000 | Susugan ang #2 - Taasan ang pagpopondo | |||
HNTB Corporation | $29,600,000 | $5,863,574 | $7,285,485 | $22,314,515 | $0 | $29,600,000 | Susugan ang #3 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Subtotal | $75,600,000 | $5,863,574 | $53,285,485 | $22,314,515 | $4,880,597 | $75,600,000 | ||||
Inter-Con Security Systems, Inc. | 2/1/19 | 7/31/19 | NA | $50,000 | $11,697 | $22,303 | $27,697 | $50,000 | $50,000 | Mga serbisyo sa security guard - Fresno Office |
Kumpanya ng JG Boswell | 6/30/15 | 12/31/19 | NA | $285,100 | $98,399 | $43,865 | $241,235 | $98,399 | $285,100 | Suriin ang mga salungatan sa mga pasilidad |
Kumpanya ng JG Boswell | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Kumpanya ng JG Boswell | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $285,100 | $98,399 | $43,865 | $241,235 | $98,399 | $285,100 | ||||
Kadesh & Associates, LLC | 12/24/14 | 12/31/19 | NA | $96,000 | $0 | $96,000 | $0 | $0 | $96,000 | Pagkonsulta sa pederal at pang-regulasyon |
Kadesh & Associates, LLC | $192,000 | $0 | $192,000 | $0 | $0 | $192,000 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Kadesh & Associates, LLC | $192,000 | $88,667 | $100,400 | $91,600 | $70,400 | $192,000 | Susugan ang #2 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $480,000 | $88,667 | $388,400 | $91,600 | $70,400 | $480,000 | ||||
Pangangalaga sa Ilog ng Kings | 9/21/11 | 12/31/19 | NA | $49,879 | $3,752 | $43,135 | $6,744 | $3,752 | $49,879 | Suriin ang mga salungatan sa mga utility |
Pangangalaga sa Ilog ng Kings | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Pangangalaga sa Ilog ng Kings | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $49,879 | $3,752 | $43,135 | $6,744 | $3,752 | $49,879 | ||||
Kleinfelder, Inc. | 12/9/16 | 8/31/19 | 25.4% | $28,000,000 | $6,794,700 | $8,353,765 | $19,646,235 | $8,253,660 | $28,000,000 | Mga serbisyo sa pagsisiyasat ng geotechnical site |
Kleinfelder, Inc. | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Suriin ang saklaw ng trabaho | |||
Kleinfelder, Inc. | -$10,000,000 | $0 | $0 | -$10,000,000 | $0 | -$10,000,000 | Susugan ang #2 - Bawasan ang pagpopondo | |||
Subtotal | $18,000,000 | $6,794,700 | $8,353,765 | $9,646,235 | $8,253,660 | $18,000,000 | ||||
KPMG (Payo sa Pinansyal) | 6/23/16 | 6/14/20 | 19.6% | $37,152,950 | $3,867,350 | $32,056,601 | $5,096,350 | $9,375,036 | $37,152,950 | Tagapayo sa pananalapi - Pangunahin |
KPMG LLP | 6/29/18 | 11/30/19 | NA | $1,500,000 | $1,288,381 | $211,619 | $1,288,381 | $1,500,000 | $1,500,000 | Pagkonsulta sa IT |
LexisNexis * | NA | $4,720 | $4,720 | $0 | $4,720 | $4,720 | $4,720 | IT Software | ||
Awtoridad ng Transporter ng Transporter ng Los Angeles County (LACMTA) | 4/10/15 | 8/30/19 | NA | $750,000 | $150,000 | $0 | $750,000 | $150,000 | $750,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Awtoridad ng Transporter ng Transporter ng Los Angeles County | 6/1/16 | 6/30/21 | NA | $15,000,000 | $193,094 | $14,806,906 | $193,094 | $193,094 | $15,000,000 | Pamamahala ng proyekto at kontrol sa kalidad para sa mga aktibidad na nauugnay sa Metro Link |
Awtoridad ng Transporter ng Transporter ng Los Angeles County | $3,726,102 | $1,356,906 | $0 | $3,726,102 | $1,613,276 | $3,726,102 | Susugan ang #1 - Taasan ang pagpopondo | |||
Awtoridad ng Transporter ng Transporter ng Los Angeles County | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Awtoridad ng Transporter ng Transporter ng Los Angeles County | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #3 - Palawakin ang term ng kontrata | |||
Subtotal | $18,726,102 | $1,550,000 | $14,806,906 | $3,919,196 | $1,806,370 | $18,726,102 | ||||
Lorman Business Center, Inc. dba Lorman Education Services | 3/1/19 | 2/28/20 | NA | $687 | $687 | $0 | $687 | $0 | $687 | Legal na Pagsasanay |
Loss Protection & Investigations, Inc. | 8/16/18 | 6/30/21 | NA | $1,000 | $273 | $60 | $940 | $333 | $1,000 | Mga serbisyo sa pagkasira ng dokumento |
Awtoridad ng Transporter ng Transporter ng Los Angeles County | 5/1/18 | 12/31/23 | NA | $76,665,000 | $14,147,000 | $0 | $76,665,000 | $14,147,000 | $76,665,000 | Kontrata sa konstruksyon para sa paghihiwalay ng grade |
Kagawaran ng Tubig at Lakas ng Los Angeles | 1/6/17 | 6/30/19 | NA | $1,400,000 | $1,324,534 | $75,466 | $1,324,534 | $1,324,534 | $1,400,000 | Magsagawa ng mga pag-aaral ng pagiging posible at pag-aaral ng solong yugto ng epekto o mga pagsusuri na nauugnay sa LADWP electrical grid |
Madera Irrigation District | 10/27/16 | 12/31/19 | NA | $20,000 | $15,000 | $0 | $20,000 | $15,000 | $20,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Madera Irrigation District | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $20,000 | $15,000 | $0 | $20,000 | $15,000 | $20,000 | ||||
Mark Thomas at Kumpanya | 3/28/14 | 6/30/21 | 30.7% | $3,200,000 | $0 | $3,200,000 | $0 | $0 | $3,200,000 | Kumuha ng mga kinakailangang survey sa lupa na may tama |
Mark Thomas at Kumpanya | $600,000 | $0 | $600,000 | $0 | $0 | $600,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Mark Thomas at Kumpanya | $1,200,000 | $107,184 | $1,092,814 | $107,186 | $107,184 | $1,200,000 | Susugan ang #2 - Taasan ang term ng kontrata; dagdagan ang pondo | |||
Mark Thomas at Kumpanya | $500,000 | $500,000 | $0 | $500,000 | $0 | $500,000 | Susugan ang #3 - Taasan ang pagpopondo | |||
Mark Thomas at Kumpanya | $3,025,000 | $466,401 | $0 | $3,025,000 | $0 | $3,025,000 | Susugan ang #4 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Subtotal | $8,525,000 | $1,073,584 | $4,892,814 | $3,632,186 | $107,184 | $8,525,000 | ||||
Mayer Brown LLP | 11/17/15 | 12/31/20 | NA | $3,000,000 | $66,674 | $1,665,652 | $1,334,348 | $66,674 | $3,000,000 | Legal na pagsusuri at suporta na nauugnay sa disenyo-build |
Mayer Brown LLP | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata; baguhin ang saklaw ng trabaho | |||
Mayer Brown LLP | -$1,200,000 | $0 | $0 | -$1,200,000 | $0 | -$1,200,000 | Susugan ang #1 - Palawakin ang term ng kontrata; bawasan ang pondo | |||
Subtotal | $1,800,000 | $66,674 | $1,665,652 | $134,348 | $66,674 | $1,800,000 | ||||
Merced Irrigation District | 2/21/17 | 6/30/20 | NA | $58,850 | $47,521 | $0 | $58,850 | $47,521 | $58,850 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Merced Irrigation District | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $58,850 | $47,521 | $0 | $58,850 | $47,521 | $58,850 | ||||
Midtown Stationers * | 0.0% | $3,112 | $3,112 | $0 | $3,112 | $0 | $3,112 | Mga kagamitan sa opisina | ||
National Marine Fisheries Service (WCR-1701) | 12/21/18 | 3/30/23 | NA | $690,236 | $142,240 | $10,350 | $679,886 | $0 | $690,236 | Tumulong sa pagsusuri ng mga hamon sa kapaligiran |
Nossaman (Tandaan 13) | 4/24/09 | 12/31/20 | 2.2% | $500,000 | $0 | $500,000 | $0 | $0 | $500,000 | Serbisyong Legal |
Nossaman | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Nossaman | $700,000 | $0 | $700,000 | $0 | $0 | $700,000 | Susugan ang #2 - Suriin ang saklaw ng trabaho | |||
Nossaman | $4,700,000 | $0 | $4,700,000 | $0 | $0 | $4,700,000 | Susugan ang #3 - Palawakin ang term ng kontrata; dagdagan ang pondo; baguhin ang saklaw ng trabaho | |||
Nossaman | $1,475,000 | $0 | $1,475,000 | $0 | $0 | $1,475,000 | Susugan ang #4 - Palawakin ang term ng kontrata; dagdagan ang pondo; baguhin ang saklaw ng trabaho | |||
Nossaman | $7,125,000 | $0 | $7,125,000 | $0 | $0 | $7,125,000 | Susugan ang #5 - Palawakin ang term ng kontrata; dagdagan ang pondo; baguhin ang saklaw ng trabaho | |||
Nossaman | $2,500,000 | $0 | $2,500,000 | $0 | $0 | $2,500,000 | Susugan ang #6 - Taasan ang pagpopondo; baguhin ang saklaw ng trabaho | |||
Nossaman | $2,000,000 | $18,228 | $1,981,772 | $18,228 | $589,980 | $2,000,000 | Susugan ang #7 - Taasan ang pagpopondo; baguhin ang Saklaw ng Trabaho | |||
Nossaman | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #8 - Palawakin ang term ng kontrata | |||
Nossaman | $0 | $0 | $0 | $0 | $0 | $0 | Baguhin ang #9 - Palawakin ang term ng kontrata | |||
Nossaman | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #10 - Palawakin ang term ng kontrata | |||
Nossaman | $3,500,000 | $1,033,059 | $0 | $3,500,000 | $0 | $3,500,000 | Susugan ang #11 - Taasan ang pagpopondo | |||
Subtotal | $22,500,000 | $1,051,286 | $18,981,772 | $3,518,228 | $589,980 | $22,500,000 | ||||
O'Dell Engineering Inc. | 3/28/14 | 6/30/21 | 99.8% | $3,200,000 | $0 | $3,200,000 | $0 | $0 | $3,200,000 | Kumuha ng mga kinakailangang survey sa lupa na may tama |
O'Dell Engineering Inc. | $600,000 | $0 | $600,000 | $0 | $0 | $600,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
O'Dell Engineering Inc. | $1,493,633 | $944,818 | $548,815 | $944,818 | $1,225,000 | $1,493,633 | Susugan ang #2 - Taasan ang pagpopondo | |||
O'Dell Engineering Inc. | $1,200,000 | $166,072 | $0 | $1,200,000 | $0 | $1,200,000 | Susugan ang #3 - Taasan ang pagpopondo | |||
O'Dell Engineering Inc. | $3,325,000 | $0 | $0 | $3,325,000 | $0 | $3,325,000 | Susugan ang #4 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Subtotal | $9,818,633 | $1,110,890 | $4,348,815 | $5,469,818 | $1,225,000 | $9,818,633 | ||||
O'Dell Engineering | 9/2/16 | 10/31/20 | 100.0% | $5,000,000 | $1,242,683 | $1,708,374 | $3,291,626 | $1,394,908 | $5,000,000 | Mga serbisyo sa engineering at scoping na tama |
Office Pro * | 0.0% | $78 | $78 | $0 | $78 | $78 | $78 | Mga kagamitan sa opisina | ||
O'Mvetny & Meyers LLP | 9/11/13 | 12/31/20 | NA | $1,999,510 | $0 | $1,999,510 | $0 | $0 | $1,999,510 | Serbisyong Legal |
O'Mvetny & Meyers LLP | $2,500,490 | $621,376 | $1,404,153 | $1,096,337 | $917,408 | $2,500,490 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
O'Mvetny & Meyers LLP | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
O'Mvetny & Meyers LLP | $500,000 | $0 | $0 | $500,000 | $0 | $500,000 | Susugan ang #3 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $5,000,000 | $621,376 | $3,403,663 | $1,596,337 | $917,408 | $5,000,000 | ||||
OnTrac * | NA | $650 | $299 | $351 | $299 | $299 | $650 | Maliit na paghahatid ng parsela | ||
Orange County Transport Agency (OCTA) | 10/26/12 | 1/31/21 | NA | $750,000 | $150,000 | $250 | $749,750 | $150,000 | $750,000 | Mga plano sa engineering, disenyo at pagtatantya sa gastos |
Orange County Transport Agency (OCTA) | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Orange County Transport Agency (OCTA) | -$450,000 | $0 | $0 | -$450,000 | $0 | -$450,000 | Susugan ang #2 - Palawakin ang term ng kontrata; bawasan ang pondo | |||
Subtotal | $300,000 | $150,000 | $250 | $299,750 | $150,000 | $300,000 | ||||
Overland, Pacific & Cutler, Inc. | 3/20/17 | 2/28/21 | 1.0% | $7,330,000 | $2,833,216 | $2,533,510 | $4,796,490 | $3,950,000 | $7,330,000 | Magbigay ng mga serbisyong right-of-way at real estate |
Overland, Pacific & Cutler, Inc. | $3,500,000 | $0 | $0 | $3,500,000 | $0 | $3,500,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Subtotal | $10,830,000 | $2,833,216 | $2,533,510 | $8,296,490 | $3,950,000 | $10,830,000 | ||||
Pacific Bell Telephone Company dba AT&T | 3/1/16 | 1/31/20 | NA | $3,000,000 | $153,036 | $2,846,964 | $153,036 | $153,036 | $3,000,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Pacific Bell Telephone Company dba AT&T | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $3,000,000 | $153,036 | $2,846,964 | $153,036 | $153,036 | $3,000,000 | ||||
Pacific Bell Telephone Company dba AT&T | 5/19/16 | 12/31/20 | NA | $14,740,000 | $6,582,633 | $6,757,064 | $7,982,936 | $5,070,297 | $14,740,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Pacific Bell Telephone Company dba AT&T | $11,543,753 | $0 | $0 | $11,543,753 | $0 | $11,543,753 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $26,283,753 | $6,582,633 | $6,757,064 | $19,526,689 | $5,070,297 | $26,283,753 | ||||
Pacific Bell Telephone Company dba AT&T | 5/19/16 | 12/31/19 | NA | $481,120 | $87,164 | $326,192 | $154,928 | $114,360 | $481,120 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Pacific Bell Telephone Company dba AT&T | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $481,120 | $87,164 | $326,192 | $154,928 | $114,360 | $481,120 | ||||
Kumpanya ng Pacific Gas at Electric | 8/31/15 | 6/30/19 | NA | $27,000,000 | $2,899,651 | $7,253,087 | $19,746,913 | $16,233,000 | $27,000,000 | CP1 - paglilipat ng mga pasilidad |
Kumpanya ng Pacific Gas at Electric | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Suriin ang saklaw ng trabaho | |||
Subtotal | $27,000,000 | $2,899,651 | $7,253,087 | $19,746,913 | $16,233,000 | $27,000,000 | ||||
Kumpanya ng Pacific Gas at Electric | 1/9/17 | 1/30/21 | NA | $36,034,000 | $1,936,463 | $6,531,494 | $29,502,506 | $18,301,498 | $36,034,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Kumpanya ng Pacific Gas at Electric | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $36,034,000 | $1,936,463 | $6,531,494 | $29,502,506 | $18,301,498 | $36,034,000 | ||||
Peninsula Corridor Joint Powers Board (PCJPB) | 12/6/17 | 10/2/19 | NA | $1,000,000 | $465,625 | $534,375 | $465,625 | $1,000,000 | $1,000,000 | Mga pagbabago sa Mga Pagsasaayos ng Pole ng OCS |
Peninsula Corridor Joint Powers Board (PCJPB) | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $1,000,000 | $465,625 | $534,375 | $465,625 | $1,000,000 | $1,000,000 | ||||
Peninsula Corridor Joint Powers Board (PCJPB) | 11/18/16 | 6/30/21 | NA | $113,000,000 | $2,147,330 | $106,810,808 | $6,189,192 | $2,147,330 | $113,000,000 | Mga gastos sa pagbuo ng proyekto, electrification at materyales |
Peninsula Corridor Joint Powers Board (PCJPB) | 6/23/17 | 6/30/21 | NA | $84,000,000 | $8,898,183 | $33,092,201 | $50,907,799 | $41,990,384 | $84,000,000 | Kontrata sa konstruksyon para sa paghihiwalay ng grade |
Peninsula Corridor Joint Powers Board (Caltrain) | 9/1/18 | 12/31/22 | NA | $600,000,000 | $555,034,904 | $44,965,096 | $555,034,904 | $0 | $600,000,000 | Mga gastos sa pagbuo ng proyekto, electrification at materyales |
Peninsula Corridor Joint Powers Board (Caltrain) | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang # 1 - Palawakin ang term ng kontrata | |||
Subtotal | $600,000,000 | $555,034,904 | $44,965,096 | $555,034,904 | $0 | $600,000,000 | ||||
Perkins Coie, LLP | 11/3/15 | 12/31/20 | NA | $500,000 | $0 | $500,000 | $0 | $0 | $500,000 | Payo at payo tungkol sa mga isyu na pinapayagan ang kapaligiran |
Perkins Coie, LLP | $500,000 | $0 | $500,000 | $0 | $352,993 | $500,000 | Susugan ang #1 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Perkins Coie, LLP | $4,000,000 | $1,574,538 | $238,949 | $3,761,051 | $0 | $4,000,000 | Susugan ang #2 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Subtotal | $5,000,000 | $1,574,538 | $1,238,949 | $3,761,051 | $352,993 | $5,000,000 | ||||
Pitney Bowes * | 83.2% | $990 | $166 | $824 | $166 | $0 | $990 | Pagrenta ng metro ng selyo | ||
Placeworks, Inc. | 8/5/16 | 5/31/21 | 30.6% | $4,900,000 | $959,798 | $108,373 | $4,791,627 | $1,000,000 | $4,900,000 | Serbisyong pangkalikasan |
Kumpanya ng Poso Canal | 1/24/17 | 6/30/20 | NA | $61,251 | $58,648 | $1,051 | $60,200 | $58,648 | $61,251 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Kumpanya ng Poso Canal | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $61,251 | $58,648 | $1,051 | $60,200 | $58,648 | $61,251 | ||||
Politico Pro * | NA | $22,817 | $11,577 | $11,240 | $11,577 | $11,577 | $22,817 | Subscription | ||
Politico Pro * | NA | $9,122 | $9,122 | $0 | $9,122 | $9,122 | $9,122 | Subscription | ||
Awtoridad sa industriya ng bilangguan (PIA) * | NA | $25,715 | $0 | $25,715 | $0 | $0 | $25,715 | Kasangkapan sa opisina | ||
Awtoridad sa industriya ng bilangguan (PIA) * | NA | $11,112 | $0 | $11,112 | $0 | $117 | $11,112 | Kasangkapan sa opisina | ||
Awtoridad sa industriya ng bilangguan (PIA) * | NA | $300,000 | $209,429 | $90,571 | $209,429 | $0 | $300,000 | Modular na kasangkapan | ||
Awtoridad sa industriya ng bilangguan (PIA) * | NA | $397 | $397 | $0 | $397 | $397 | $397 | Kagamitan sa kaligtasan - Mga safety vests | ||
Awtoridad sa industriya ng bilangguan (PIA) * | NA | $107,886 | $107,886 | $0 | $107,886 | $107,886 | $107,886 | Kasangkapan sa opisina | ||
Limitado ang Advisory ng Pananalapi ng Project | 12/18/15 | 10/10/21 | 7.1% | $4,000,000 | $1,250,000 | $1,356,345 | $2,643,655 | $1,250,000 | $4,000,000 | Mga ulat sa isyu ayon sa seksyon ng Mga Street at Highway ng California na seksyon 2704.08 (d) (2) |
Limitado ang Advisory ng Pananalapi ng Project | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Limitado ang Advisory ng Pananalapi ng Project | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $4,000,000 | $1,250,000 | $1,356,345 | $2,643,655 | $1,250,000 | $4,000,000 | ||||
PTG Pacheco Pass Corridor (Tandaan 13) | 12/9/08 | 6/30/19 | 11.5% | $55,000,000 | $0 | $55,000,000 | $0 | $0 | $55,000,000 | Pagbuo ng data ng engineering, pagpaplano at pangkapaligiran |
PTG Pacheco Pass Corridor | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata; baguhin ang saklaw ng trabaho | |||
PTG Pacheco Pass Corridor | $9,300,000 | $0 | $9,300,000 | $0 | $0 | $9,300,000 | Susugan ang #2 - Palawakin ang term ng kontrata; dagdagan ang pondo; baguhin ang saklaw ng trabaho | |||
PTG Pacheco Pass Corridor | $8,940,000 | $0 | $8,940,000 | $0 | $0 | $8,940,000 | Susugan ang #3 - Palawakin ang term ng kontrata; dagdagan ang pondo; baguhin ang saklaw ng trabaho | |||
PTG Pacheco Pass Corridor | $4,000,000 | $0 | $4,000,000 | $0 | $0 | $4,000,000 | Susugan ang #4 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
PTG Pacheco Pass Corridor | $3,000,000 | $1,009,769 | $840,096 | $2,159,904 | $278,345 | $3,000,000 | Susugan ang #5 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $80,240,000 | $1,009,769 | $78,080,096 | $2,159,904 | $278,345 | $80,240,000 | ||||
Lupon ng Relasyong Pang-empleyo ng Publiko | 11/2/18 | 7/31/19 | NA | $10,000 | $10,000 | $0 | $10,000 | $10,000 | $10,000 | Mga Serbisyo sa pamamagitan |
Mga Serbisyo sa Patlang ng RailPros | 6/19/18 | 6/30/20 | NA | $375,000 | $77,648 | $72,352 | $302,648 | $150,000 | $375,000 | CP1 - Mga inspeksyon sa paglilipat ng utility |
Mga Serbisyo sa Patlang ng RailPros | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata; baguhin ang saklaw ng trabaho | |||
Subtotal | $375,000 | $77,648 | $72,352 | $302,648 | $150,000 | $375,000 | ||||
Pamamahala ng Realty Property | 11/27/17 | 6/30/21 | 76.2% | $1,000,000 | $274,475 | $205,764 | $794,236 | $250,000 | $1,000,000 | Pamamahala ng kontrata ng mga nakuha na site ng ROW (CP 4) |
Pamamahala ng Realty Property | 9/5/17 | 1/30/21 | 26.9% | $1,000,000 | $0 | $1,000,000 | $0 | $250,000 | $1,000,000 | Pamamahala ng kontrata ng mga nakuha na site ng ROW (CP 1) |
Pamamahala ng Realty Property | $250,000 | $212,137 | $37,863 | $212,137 | $0 | $250,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Subtotal | $1,250,000 | $212,137 | $1,037,863 | $212,137 | $250,000 | $1,250,000 | ||||
Pamamahala ng Realty Property | 9/5/17 | 1/30/21 | 34.2% | $1,000,000 | $648,486 | $351,514 | $648,486 | $333,333 | $1,000,000 | Pamamahala ng kontrata ng mga nakuha na site ng ROW (CP 2) |
Pamamahala ng Realty Property | 9/5/17 | 1/30/21 | 45.2% | $1,000,000 | $377,118 | $196,839 | $803,161 | $350,000 | $1,000,000 | Pamamahala ng kontrata ng mga nakuha na site ng ROW (CP 3) |
Ang mga rehistro ng Unibersidad ng California, Berkeley, na pagkatapos ay tinukoy bilang "Unibersidad o UC Berkeley" | 8/10/18 | 6/30/20 | NA | $178,000 | $89,000 | $0 | $178,000 | $89,000 | $178,000 | Patakaran sa seismic at mga eksperto sa teknikal na kasanayan |
Remy Moose Manley, LLP | 9/13/12 | 12/31/20 | NA | $500,000 | $0 | $500,000 | $0 | $0 | $500,000 | Naranasan ang mga serbisyong ligal sa proseso ng pagsisiyasat sa kongreso |
Remy Moose Manley, LLP | $500,000 | $0 | $500,000 | $0 | $0 | $500,000 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo; baguhin ang saklaw ng trabaho | |||
Remy Moose Manley, LLP | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Suriin ang saklaw ng trabaho | |||
Remy Moose Manley, LLP | $750,000 | $77,414 | $672,586 | $77,414 | $398,663 | $750,000 | Susugan ang #3 - Palawakin ang term ng kontrata; dagdagan ang pondo; baguhin ang saklaw ng trabaho | |||
Remy Moose Manley, LLP | $500,000 | $500,000 | $500,000 | $500,000 | $500,000 | Susugan ang #4 - Palawakin ang term ng kontrata; dagdagan ang pondo | ||||
Remy Moose Manley, LLP | $1,500,000 | $312,340 | $0 | $1,500,000 | $0 | $1,500,000 | Susugan ang #5 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $3,750,000 | $889,754 | $1,672,586 | $2,077,414 | $898,663 | $3,750,000 | ||||
Rutan & Tucker | 8/14/15 | 12/31/20 | NA | $3,000,000 | $0 | $3,000,000 | $0 | $907,906 | $3,000,000 | Sa labas ng ligal na payo upang makatulong sa disenyo ng pagbuo ng konstruksyon sa pagkuha ng trabaho at mga kaugnay na usapin |
Rutan & Tucker | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Rutan & Tucker | $3,400,000 | $318,071 | $1,347,692 | $2,052,308 | $0 | $3,400,000 | Susugan ang #2 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $6,400,000 | $318,071 | $4,347,692 | $2,052,308 | $907,906 | $6,400,000 | ||||
Distrito ng Tubig ng San Benito County | 1/9/17 | 12/31/19 | NA | $45,200 | $26,840 | $1,772 | $43,428 | $26,840 | $45,200 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Distrito ng Tubig ng San Benito County | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $45,200 | $26,840 | $1,772 | $43,428 | $26,840 | $45,200 | ||||
San Joaquin Regional Rail Commission (SJRRC) | 12/18/12 | 6/30/19 | NA | $750,000 | $101,834 | $648,166 | $101,834 | $101,834 | $750,000 | Paghahanda at pagsusuri ng mga paunang at huling plano sa disenyo ng engineering |
San Joaquin Regional Rail Commission (SJRRC) | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
San Joaquin Regional Rail Commission (SJRRC) | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $750,000 | $101,834 | $648,166 | $101,834 | $101,834 | $750,000 | ||||
San Joaquin Valley Air Pollution Control District | 7/23/14 | 7/31/28 | NA | $1,705,472 | $200,000 | $1,364,377 | $341,095 | $200,000 | $1,705,472 | Pagpapagaan ng kapaligiran |
San Joaquin Valley Air Pollution Control District | 6/26/15 | 7/31/28 | NA | $367,829 | $73,566 | $294,263 | $73,566 | $73,566 | $367,829 | Mga gastos sa pagpapatupad para sa kasunduan sa pagbawas ng kusang-loob na pagpapalabas |
San Joaquin Valley Air Pollution Control District | 1/13/16 | 7/31/28 | NA | $10,806,923 | $1,000,000 | $8,645,538 | $2,161,385 | $1,000,000 | $10,806,923 | Gastos upang mabawi ang polusyon sa hangin na sanhi ng konstruksyon sa loob ng mga hangganan ng Distrito |
San Joaquin Valley Railroad Co. | 8/28/15 | 6/30/20 | NA | $5,000,000 | $564,704 | $1,634,312 | $3,365,688 | $1,040,000 | $5,000,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
San Joaquin Valley Air Pollution Control District | 9/16/16 | 6/30/26 | NA | $3,562,246 | $712,449 | $2,849,797 | $712,449 | $712,449 | $3,562,246 | Kasunduang Pagbawas ng Boluntaryong Mga Pagpapalabas |
San Jose State University Research Foundation | 3/14/17 | 12/31/19 | NA | $665,000 | $0 | $0 | $665,000 | $0 | $665,000 | Pananaliksik, paglipat ng teknolohiya, pag-unlad ng lakas ng trabaho, edukasyon at pagsasanay |
San Luis Delta - Awtoridad ng Mendota Water | 1/9/17 | 12/31/19 | NA | $58,740 | $55,097 | $3,643 | $55,097 | $55,097 | $58,740 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
San Luis Delta - Awtoridad ng Mendota Water | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $58,740 | $55,097 | $3,643 | $55,097 | $55,097 | $58,740 | ||||
Awtoridad ng Transportasyon ng Santa Clara Valley | 3/1/19 | 12/31/20 | NA | $1,000,000 | $605,000 | $0 | $1,000,000 | $0 | $1,000,000 | Paunang disenyo - istasyon |
Kalihim ng Estado ng California * | NA | $2,200 | $0 | $2,200 | $0 | $650 | $2,200 | Pag-arkila ng pasilidad sa Lupon ng Pagpupulong | ||
Kalihim ng Estado ng California * | NA | $1,125 | $1,125 | $0 | $1,125 | $1,125 | $1,125 | Pag-upa sa auditoryum | ||
Sener Engineering at System | 4/24/15 | 12/31/21 | 25.2% | $56,000,000 | $883,972 | $55,116,028 | $883,972 | $7,149,603 | $56,000,000 | Preliminary engineering at proyekto-tiyak na gawaing pangkapaligiran |
Sener Engineering at System | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Suriin ang saklaw ng trabaho | |||
Sener Engineering at System | $8,901,223 | $835,685 | $0 | $8,901,223 | $0 | $8,901,223 | Susugan ang #2 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $64,901,223 | $1,719,657 | $55,116,028 | $9,785,195 | $7,149,603 | $64,901,223 | ||||
Shute, Mihaly & Weinberger, LLP | 10/11/17 | 12/31/20 | NA | $250,000 | $233,585 | $16,415 | $233,585 | $233,585 | $250,000 | Pagpapagaan ng kapaligiran |
Shute, Mihaly & Weinberger, LLP | $250,000 | $0 | $0 | $250,000 | $0 | $250,000 | Susugan ang #1 - Palawakin ang term ng kontrata, dagdagan ang pagpopondo; baguhin ang saklaw ng trabaho | |||
Subtotal | $500,000 | $233,585 | $16,415 | $483,585 | $233,585 | $500,000 | ||||
Mga Produktong Maliit na Negosyo * | NA | $6,197 | $0 | $6,197 | $0 | $6,197 | $6,197 | Mga kagamitan sa opisina | ||
Awtoridad ng Rehiyon ng Rehiyon ng Timog California | 6/26/15 | 9/30/19 | NA | $750,000 | $280,869 | $323,577 | $426,423 | $438,521 | $750,000 | Bumuo ng data ng engineering, pagpaplano at pangkapaligiran |
Sprint Communication Company LP | 3/14/17 | 6/30/19 | NA | $100,000 | $50,000 | $0 | $100,000 | $50,000 | $100,000 | Sinasalungat ang mga salungatan sa mga utility |
Sprint Communication Company LP | 3/14/17 | 6/30/19 | NA | $100,000 | $50,000 | $0 | $100,000 | $50,000 | $100,000 | Sinasalungat ang mga salungatan sa mga utility |
Stamp.com * | NA | $1,735 | $396 | $1,339 | $396 | $0 | $1,735 | Pag-upa sa metro ng mail | ||
Stamp.com * | NA | $1,260 | $1,050 | $210 | $1,050 | $1,260 | $1,260 | Pag-renew ng serbisyo | ||
Opisina ng Controller ng Estado (SCO) | 7/18/16 | 6/30/19 | NA | $240,000 | $36,750 | $88,020 | $151,980 | $48,915 | $240,000 | Mapabilis ang mga serbisyo sa warranty |
Opisina ng Controller ng Estado | 9/1/18 | 6/30/19 | NE | $2,350 | $0 | $2,350 | $0 | $0 | $2,350 | Sistema ng Pagkuha ng Impormasyon sa Pamamahala |
Lupon ng Kontrol sa Mga Yamang Tubig ng Estado | 2/17/17 | 12/1/19 | NA | $1,161,000 | $391,472 | $141,221 | $1,019,779 | $387,000 | $1,161,000 | Pinabilis ng mga Serbisyo ng Tubig ng Estado ang mga serbisyo |
Strato Communication, Inc * | 0.0% | $39,970 | $39,970 | $0 | $39,970 | $39,970 | $39,970 | Kagamitan sa IT | ||
Isinama ang STV | 3/27/15 | 1/31/21 | 79.1% | $51,000,000 | $0 | $47,495,446 | $3,504,554 | $0 | $51,000,000 | Preliminary engineering at proyekto-tiyak na gawaing pangkapaligiran |
Isinama ang STV | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Suriin ang saklaw ng trabaho | |||
Isinama ang STV | $12,483,097 | $7,023,199 | $0 | $12,483,097 | $0 | $12,483,097 | Susugan ang #2 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $63,483,097 | $7,023,199 | $47,495,446 | $15,987,651 | $0 | $63,483,097 | ||||
Telenet VoIP * | NA | $9,554 | $0 | $0 | $9,554 | $9,554 | $9,554 | Kagamitan sa IT | ||
Thomson Reuters* | 100.0% | $765 | $0 | $765 | $0 | $403 | $765 | NEPA Law and Litigation 2 -yr. subscription | ||
TIG * | 0.0% | $6,436 | $0 | $0 | $6,436 | $6,436 | $6,436 | Kagamitan sa IT | ||
Hanggang sa | 9/12/17 | 10/31/20 | 43.3% | $4,000,000 | $848,310 | $812,473 | $3,187,527 | $3,396,377 | $4,000,000 | Mga serbisyo sa suporta sa engineering at survey ng ROW |
Bayan ng Atherton | 1/25/17 | 12/31/19 | NA | $50,000 | $40,000 | $0 | $50,000 | $40,000 | $50,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad na maaaring mangailangan ng paglipat |
Bayan ng Atherton | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata; baguhin ang saklaw ng trabaho | |||
Subtotal | $50,000 | $40,000 | $0 | $50,000 | $40,000 | $50,000 | ||||
Tutor Perini / Zachry / Parsons, isang Pinagsamang Venture | 8/16/13 | 8/31/19 | 24.4% | $1,022,988,000 | $89,674,461 | $933,313,539 | $89,674,461 | $229,414,930 | $1,022,988,000 | Proyekto sa Konstruksiyon |
Tutor Perini / Zachry / Parsons, isang Pinagsamang Venture | $552,670,155 | $202,982,436 | $0 | $552,670,155 | $202,982,436 | $552,670,155 | Kabuuan ng 261 naipatupad na mga order ng pagbabago | |||
Subtotal | $1,575,658,155 | $292,656,897 | $933,313,539 | $642,344,616 | $432,397,366 | $1,575,658,155 | ||||
TY Lin International | 2/20/14 | 1/31/21 | 28.4% | $46,100,000 | $0 | $46,100,000 | $0 | $0 | $46,100,000 | Magbigay ng Project-Level EIR / EIS & Preliminary Engineering para sa Bakersfield - Palmdale |
TY Lin International | $22,100,000 | $3,976,520 | $13,833,736 | $8,266,264 | $7,792,711 | $22,100,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
TY Lin International | -$3,000,000 | $0 | $0 | -$3,000,000 | $0 | -$3,000,000 | Susugan ang #2 - Bawasan ang pagpopondo | |||
TY Lin International | $7,458,068 | $0 | $0 | $7,458,068 | $0 | $7,458,068 | Susugan ang #3 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $72,658,068 | $3,976,520 | $59,933,736 | $12,724,332 | $7,792,711 | $72,658,068 | ||||
UIC International Union of Railways | 1/1/18 | 12/31/22 | NA | $65,296 | $0 | $65,296 | $0 | $65,296 | $65,296 | Pagiging miyembro ng Railway Operations |
Universal Field Services, Inc. | 3/20/17 | 2/28/21 | 10.7% | $7,330,000 | $2,252,125 | $3,895,837 | $3,434,163 | $3,400,000 | $7,330,000 | Magbigay ng mga serbisyong right-of-way at real estate |
Universal Field Services, Inc. | $3,500,000 | $0 | $0 | $3,500,000 | $0 | $3,500,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Subtotal | $10,830,000 | $2,252,125 | $3,895,837 | $6,934,163 | $3,400,000 | $10,830,000 | ||||
UPRR (Tandaan 13) | 6/6/12 | 12/31/19 | NA | $750,000 | $0 | $750,000 | $0 | $0 | $750,000 | Suriin ang mga guhit ng disenyo |
UPRR | $850,000 | $36,133 | $813,867 | $36,133 | $36,133 | $850,000 | Susugan ang #1 - Taasan ang pagpopondo; baguhin ang saklaw ng trabaho | |||
UPRR | $3,400,000 | $3,037,788 | $0 | $3,400,000 | $3,399,995 | $3,400,000 | Susugan ang #2 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Subtotal | $5,000,000 | $3,073,921 | $1,563,867 | $3,436,133 | $3,436,129 | $5,000,000 | ||||
Union Pacific Railway Company ("UPRR") | 12/22/14 | 9/30/20 | NA | $39,400,000 | $5,909,873 | $33,490,127 | $5,909,873 | $12,644,792 | $39,400,000 | Kasunduan sa engineering, konstruksyon at pagpapanatili |
Union Pacific Railway Company ("UPRR") | $29,625,000 | $6,892,152 | $0 | $29,625,000 | $0 | $29,625,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Subtotal | $69,025,000 | $12,802,024 | $33,490,127 | $35,534,873 | $12,644,792 | $69,025,000 | ||||
Mga Engineer ng US Army Corp. | 11/20/14 | 9/30/19 | NA | $1,884,657 | $635,770 | $1,248,887 | $635,770 | $747,498 | $1,884,657 | Mapabilis ang pagsusuri ng aplikasyon para sa permiso para sa saklaw ng proyekto |
Mga Engineer ng US Army Corp. | $3,429,514 | $13,798 | $0 | $3,429,514 | $670,907 | $3,429,514 | Susugan ang #1 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
Subtotal | $5,314,171 | $649,568 | $1,248,887 | $4,065,284 | $1,418,405 | $5,314,171 | ||||
US Bureau of Reclaim | 2/3/15 | 5/31/19 | NA | $236,990 | $0 | $236,990 | $0 | $0 | $236,990 | Paglutas ng mga potensyal na hamon sa mga epekto sa mapagkukunang pangkapaligiran |
US Bureau of Reclaim | $984,678 | $0 | $984,678 | $0 | $0 | $984,678 | Susugan ang #1 - Taasan ang pagpopondo; pahabain ang term ng kontrata | |||
US Bureau of Reclaim | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $1,221,668 | $0 | $1,221,668 | $0 | $0 | $1,221,668 | ||||
Kagawaran ng Agrikultura ng Estados Unidos (USDA), Serbisyo sa Kagubatan, Angeles National Forest ("US Forest Service") | 2/22/17 | 12/1/19 | NA | $516,251 | $0 | $516,250 | $1 | $0 | $516,251 | Pagsusuri sa kapaligiran at mga pahintulot |
Ahensya ng Proteksyon sa Kapaligiran ng US | 8/29/14 | 6/30/20 | NA | $692,340 | $0 | $692,340 | $0 | $0 | $692,340 | Paglutas ng mga potensyal na hamon sa mga epekto sa mapagkukunang pangkapaligiran |
Ahensya ng Proteksyon sa Kapaligiran ng US | $1,074,437 | $0 | $1,074,437 | $0 | $0 | $1,074,437 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Ahensya ng Proteksyon sa Kapaligiran ng US | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $1,766,777 | $0 | $1,766,777 | $0 | $0 | $1,766,777 | ||||
Kagawaran ng Fish and Wildlife Services ng Estados Unidos | 10/1/15 | 11/30/19 | NA | $1,291,384 | $0 | $1,291,384 | $0 | $0 | $1,291,384 | Magbigay ng mga panteknikal na tulong sa teknikal at serbisyo sa koordinasyon |
Kagawaran ng Fish and Wildlife Services ng Estados Unidos | $1,098,635 | $114,379 | $984,256 | $114,380 | $474,574 | $1,098,635 | Susugan ang #1 - Taasan ang pagpopondo; baguhin ang saklaw ng trabaho | |||
Kagawaran ng Fish and Wildlife Services ng Estados Unidos | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $2,390,019 | $114,379 | $2,275,640 | $114,380 | $474,574 | $2,390,019 | ||||
US Geological Survey | 7/10/15 | 9/30/19 | NA | $498,310 | $165,000 | $52,747 | $445,563 | $165,000 | $498,310 | Teknikal na suporta at data para sa mga isyu sa pagkalubog |
Ang Frontier California, Inc. | 9/25/14 | 12/31/19 | NA | $21,225 | $0 | $0 | $21,225 | $8,490 | $21,225 | Sinasalungat ang mga salungatan sa mga utility |
Ang Frontier California, Inc. | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Ang Frontier California, Inc. | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Suriin ang saklaw ng trabaho | |||
Ang Frontier California, Inc. | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #3 - Palawakin ang term ng kontrata | |||
Subtotal | $21,225 | $0 | $0 | $21,225 | $8,490 | $21,225 | ||||
Kumpanya ng Mga Serbisyo sa Pag-stream ng Video | 3/3/17 | 2/29/20 | NA | $100,000 | $0 | $100,000 | $0 | $26,375 | $100,000 | Mga serbisyong IT - Mga serbisyo sa streaming ng video |
Kumpanya ng Mga Serbisyo sa Pag-stream ng Video | $100,000 | $43,773 | $23,227 | $76,773 | $0 | $100,000 | Susugan ang #1 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Kumpanya ng Mga Serbisyo sa Pag-stream ng Video | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Palawakin ang term ng kontrata | |||
Subtotal | $200,000 | $43,773 | $123,227 | $76,773 | $26,375 | $200,000 | ||||
Vollmar Natural Lands Consulting, Inc. | 6/10/14 | 12/31/25 | NA | $1,852,910 | $142,379 | $1,009,438 | $843,472 | $183,879 | $1,852,910 | Pagpapagaan ng kapaligiran |
Vollmar Natural Lands Consulting, Inc. | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Suriin ang saklaw ng trabaho | |||
Subtotal | $1,852,910 | $142,379 | $1,009,438 | $843,472 | $183,879 | $1,852,910 | ||||
Volpe National Transportation Systems Center | 11/22/17 | 6/30/19 | NA | $2,500,000 | $900,000 | $1,600,000 | $900,000 | $900,000 | $2,500,000 | Pagsusuri sa Mga Dokumentong Pangkapaligiran ng HSR System |
Volpe National Transportation Systems Center | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $2,500,000 | $900,000 | $1,600,000 | $900,000 | $900,000 | $2,500,000 | ||||
Walker's Express * | 0.0% | $499 | $499 | $0 | $499 | $499 | $499 | Mga kagamitan sa opisina | ||
Walker's Express * | 0.0% | $88 | $0 | $0 | $88 | $88 | $88 | Mga kagamitan sa opisina | ||
Walker's Express * | 0.0% | $68 | $68 | $0 | $68 | $68 | $68 | Mga kagamitan sa opisina | ||
Walker's Express * | 0.0% | $277 | $275 | $0 | $277 | $277 | $277 | Mga kagamitan sa opisina | ||
Wavelength Automation, Inc. * | 93.6% | $3,042 | $194 | $2,848 | $194 | $2,574 | $3,042 | Mga serbisyo sa IT - CapitolTrack | ||
West Isle Line, Inc. | 12/21/17 | 5/31/21 | NA | $1,000,000 | $350,000 | $0 | $1,000,000 | $350,000 | $1,000,000 | Suriin ang mga guhit ng disenyo |
West Publishing Corporation, dba West, isang Negosyo sa Thomson Reuters | 9/7/17 | 6/30/20 | NA | $70,884 | $5,597 | $40,497 | $30,387 | $1,837 | $70,884 | Mga serbisyong elektronikong ligal sa silid-aklatan |
Ang West San Martin Water Works, Inc. | 10/17/16 | 6/30/20 | NA | $32,000 | $23,550 | $599 | $31,401 | $23,550 | $32,000 | Tumulong sa koordinasyon at pagsusuri ng mga pasilidad |
Ang West San Martin Water Works, Inc. | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #1 - Palawakin ang term ng kontrata | |||
Subtotal | $32,000 | $23,550 | $599 | $31,401 | $23,550 | $32,000 | ||||
Westervelt Ecological Services | 3/21/16 | 2/28/21 | 3.8% | $48,895,000 | $1,222,619 | $46,029,020 | $2,865,980 | $7,600,874 | $48,895,000 | Mga serbisyo sa pagpapagaan ng tirahan |
Westervelt Ecological Services | 4/17/19 | 2/29/20 | NA | $1,573,800 | $1,573,800 | $0 | $1,573,800 | $0 | $1,573,800 | Kredito sa pagpapagaan ng tirahan |
Wong + Harris, JV | 5/15/13 | 12/31/19 | 29.1% | $34,208,889 | $0 | $34,208,889 | $0 | $0 | $34,208,889 | Pangangasiwa sa Konstruksiyon |
Wong + Harris, JV | $6,000,000 | $0 | $6,000,000 | $0 | $0 | $6,000,000 | Susugan ang #1 - Taasan ang pagpopondo | |||
Wong + Harris, JV | $1,000,000 | $0 | $1,000,000 | $0 | $0 | $1,000,000 | Susugan ang #2 - Taasan ang pagpopondo | |||
Wong + Harris, JV | $28,500,000 | $219,558 | $14,986,072 | $13,513,928 | $13,276,475 | $28,500,000 | Susugan ang #3 - Palawakin ang term ng kontrata; dagdagan ang pondo | |||
Subtotal | $69,708,889 | $219,558 | $56,194,961 | $13,513,928 | $13,276,475 | $69,708,889 | ||||
Ang WSP USA, Inc. | 7/1/15 | 6/30/22 | 27.5% | $700,000,000 | $33,780,792 | $418,638,356 | $281,361,644 | $124,151,289 | $700,000,000 | Kasosyo sa Paghahatid ng Riles para sa mga serbisyong pangkapaligiran at konstruksyon sa engineering |
Ang WSP USA, Inc. | -$3,452,204 | $0 | $0 | -$3,452,204 | $0 | -$3,452,204 | Susugan ang #1 - Suriin ang saklaw ng trabaho; bawasan ang pondo | |||
Ang WSP USA, Inc. | $0 | $0 | $0 | $0 | $0 | $0 | Susugan ang #2 - Baguhin ang Parsons Brinkerhoff sa WSP USA, Inc. | |||
Ang WSP USA, Inc. | -$30,178,000 | $0 | $0 | -$30,178,000 | $0 | -$30,178,000 | Susugan ang #3 - Bawasan ang pagpopondo, baguhin ang saklaw ng trabaho | |||
Subtotal | $666,369,796 | $33,780,792 | $418,638,356 | $247,731,440 | $124,151,289 | $666,369,796 | ||||
Kabuuan | 21.3% | $6,658,819,301 | $1,334,044,923 | $3,396,705,962 | $3,262,113,339 | $1,325,918,584 | $6,658,819,300 |
Ginagawa ng California High-Speed Rail Authority ang bawat pagsisikap upang matiyak na ang website at ang mga nilalaman nito ay nakakatugon sa inatasang mga kinakailangan ng ADA ayon sa utos ng Estado ng California na Batayan sa Pag-access sa Nilalaman ng Web na pamantayang 2.0 Antas AA. Kung naghahanap ka para sa isang partikular na dokumento na hindi matatagpuan sa website ng California High-Speed Rail Authority, maaari kang humiling ng isang dokumento para sa ilalim ng Public Records Act sa pamamagitan ng pahina ng Public Records Act. Kung mayroon kang anumang mga katanungan tungkol sa website o mga nilalaman nito, mangyaring makipag-ugnay sa Awtoridad sa info@hsr.ca.gov.